Project Status: What's Happening Now?
  Click on Map to See Proposed Construction Phasing

 

 

Major Segments under Construction:
Construction began February 2005

  • Construction of new Collector/ Distributor ramps adjacent to I-95.  The northbound ramps are mostly completed and in service.  The southbound ramps are approximately 60% complete.
  • Widening of I-10 Westbound is ongoing.  It is approximately 50% complete
  • I-95 northbound is being reconstructed.  Work has recently commenced in this area.
  • A new flyover from I-10 EB to I-95 NB is under construction and is approximately 20% complete.
Click on Map to Enlarge

Major Segments Completed: Phases 1-4 are now completed. Work Continues on Phases 5, 6 7, and portions of Phase 10. 

  • The I-95 Northbound Collector/ Distributor Ramps are mostly completed, and in service at this time.
  • The I-95 Northbound to 1-10 Westbound flyover ramp is now complete and will be in service starting August 16.
 
 
Ramp and Road Closures: Click on Map to Enlarge
  • Starting Friday, May, 9, 2008, a new on-ramp to 1-95 North Bound from Forest St. will be open. Project signage will direct traffic to the new ramp location.